Find the information such as human life, natural resource,agriculture,forestry, biotechnology, biodiversity, wood and non-wood materials.
Blog List
Wednesday, 1 March 2017
Techno-economic comparison of three energy conversion pathways from empty fruit bunches
Published Date
Renewable Energy May 2016, Vol.90:307–318,doi:10.1016/j.renene.2016.01.030 Author
Truong Xuan Do a,b,
Young-il Lim a,,
aCoSPE, Department of Chemical Engineering, Hankyong National University, Jungangno 327, Anseong-si, Gyonggi-do 456-749 Republic of Korea
bSchool of Chemical Engineering, Hanoi University of Science and Technology, 1st Dai Co Viet, Hanoi, Viet Nam
Received 1 July 2015. Revised 1 December 2015. Accepted 6 January 2016. Available online 13 January 2016.
Highlights
•
Evaluation of techno-economic feasibility by 4-level economic potential approach.
•
Comparison of three energy conversion pathways from 400 t/d wet EFB.
•
The three pathways include fast pyrolysis, gasification and bioethanol production.
•
The fast pyrolysis and biooil upgrading plant shows the highest economic viability.
Abstract Empty fruit bunches (EFB) of oil-palm are one of the most recent renewable energy resources. The objective of this study is to find the most economically-feasible pathway among three energy conversions from 400 t/d wet EFB, which are bioethanol and jet fuel by bioconversion, combined heat and power via gasification, and hydrocarbons through fast pyrolysis and biooil upgrading. A hierarchical four-level economic potential approach (4-level EP) was employed to perform the preliminary techno-economic analysis (TEA) for the three pathways. The 4-level EP includes the input/output structure, the flowsheet structure, the heat integration (HI), and the economic feasibility. The economic potential of the three plants was compared at each level, and the most promising process among them was identified at Level 4, where economic criteria including return on investment (ROI), payback period (PBP), and internal rate of return (IRR) were evaluated. It was found that the biooil hydrocarbon plant is most economical due to the highest economic potential, ROI, and IRR. The heat consumption was reduced considerably by HI in the bioethanol and jet fuel plant. The sensitivity analysis informed that the plant size, the product yield, and the total capital investment highly influenced ROI and PBP in all three processes. Keywords
Empty fruit bunches (EFB)
Fast-pyrolysis
Gasification
Bioethanol
Economic potential
Techno-economic analysis (TEA)
Nomenclature
Abbreviations
4-level EP
Four-level hierarchical economic potential
BEJF
bioethanol and jet fuel
BOE
barrel of oil equivalent
CAPEX
capital expenditure
CEPCI
chemical engineering plant cost index
EFB
empty fruit bunches
EP
economic potential
FFB
fresh fruit bunches
FPBU
fast pyrolysis and biooil upgrading
GCHP
gasification for combined heat and power
HHV
higher heating value
HI
heat integration
IRR
internal rate of return, %
LCOE
levelized cost of electricity, $/kWhe
LHV
lower heating value
NPV
net present value, $
NRTL
non-random two-liquid
OPEX
operational expenditure
PBP
payback period, yr
PR
Peng-Robinson
PFD
process flow diagram
PoS
plot of sensitivity
REC
renewable energy certificate
ROI
return on investment, %
SRK
Soave-Redlich-Kwong
TEA
techno-economic analysis
Symbols
A
capacity, kt/yr
a
installed cost factor
b
indirect cost factor
c
project contingency factor
cr
cost of the raw material, $/kg
CAI
annualized total installed cost, $/yr
Ccat
annualized catalyst cost, $/yr
Cdep
depreciation cost, $/yr
CDI
total direct and indirect costs, $
CE
purchased equipment costs, $
CF
fixed capital investment, $
Cfix
fixed costs, $/yr
CHE
extra heat exchanger capital cost, $
CI
total installed cost, $
CID
indirect cost, $
CP
project contingency, $
CRM
raw material cost, $/yr
CT
total capital investment, $
CTP
total production cost, $/yr
CTU
total utility cost, $/yr
CTU,HI
total utility cost after heat integration, $/yr
CTUS
total utility saved by heat integration, $/yr
CW
working capital, $
d
working capital factor
E
economic potential, $/yr
Fp
mass flow rate of product, kg/yr
f
amount of byproduct or raw material per 1 kg of product, kg/kg
i
interest rate, %
I
cost index
Lcat
catalyst life time, yr
Ld
depreciation life, yr
Lp
plant life, yr
N
number of equipment
pp
market price of product, $/kg
pbp
market price of byproduct, $/kg
PASR
annual sales revenue, $/yr
Pcash
cash flow, $/yr
pcat
market price of catalyst, $/kg
PG
gross profit, $/yr
PN
net profit, $/yr
vspace
weight hourly space velocity, h−1
β
rate of corporation income tax
γ
capacity exponent
ηLHV
energy conversion efficiency based on lower heating value,%
No comments:
Post a Comment